Project Connect

Share & Bookmark, Press Enter to show all options, press Tab go to next option
Print

 Project Connect Logo with Tagline

Sign up for updates here!

Project Connect Construction is Underway

Project Connect, the City’s largest capital improvement project, is enhancing pedestrian access and safety, improving road conditions and building critical linkage through Goleta while increasing stormwater flow capacity in San Jose Creek under Hollister Bridge. Project Connect requires numerous right-of-way acquisitions and permits as well as close coordination with many local agencies including Caltrans, City of Santa Barbara, and the County of Santa Barbara.

View maps of the different project areas using the links below:

Watch our video below providing a two-year update on Project Connect, including tips on how to navigate two newly opened roundabouts in Old Town.

 

Construction Update – Summer 2026

Ekwill Street & Pine Avenue

The newly constructed roundabout is anticipated to open Friday, July 10. The one lane configuration will continue to be in place until then. Vehicles are currently regulated by temporary traffic signals, allowing movement in one direction at a time. Bicycles and vehicles share the road. Final improvements and plantings will take place for a few weeks. Please allow extra travel time and use caution when traveling through the area.

Construction activity is still underway near the roundabouts on Hollister Ave. as work continues to enhance safety and traffic flow.

Please continue to use caution and share the road with bicyclists, pedestrians and other drivers.

For additional information, or questions, please email Connect@CityofGoleta.org or call 805-690-5116.

 

Current Mitigation Planting

The City is implementing mitigation efforts to address areas where trees and vegetation were removed during construction. This work includes planting more than 3,600 native trees and plants across approximately four acres. Species include Western Sycamore, Coast Live Oak, Black Cottonwood, various Willow species, and native shrubs and grasses. Planting will take place in key open space areas including Ellwood Mesa, Lake Los Carneros, Ekwill Street, and Fowler Road and Old San Jose Creek areas.

Work is scheduled to begin June 8, 2026, and is anticipated to be completed in late Fall 2026.

Project Connect Mitigation Map

Navigating Roundabouts

The Federal Highway Administration (FHWA) developed a short video to help drivers navigate roundabouts. Click here to watch the video. Closed captions are available in numerous languages.

Drivers are navigating the new roundabout configuration, with ongoing work including temporary striping and traffic control in some areas. Final roundabout features, including landscaping and aesthetic enhancements, will be installed later this year as construction progresses.

 Hollister and Hwy 217 Roundabout Map as of March 2 2026

View a larger map here or click map above.

 

Ekwill Street - Pine Avenue Roundabout

View a larger map here or click map above.

Project Areas

Project Connect includes three project areas: Hollister Avenue, Ekwill Street and S. Kellogg Avenue / Fowler Road. Click the arrows below to learn more about each project.

Hollister Avenue / Old Town Striping Project
Hollister Avenue Bridge & Roundabouts Project
Ekwill Street & Fowler Road Extension Projects

Frequently Asked Questions

How does the contractor determine where Project Connect construction will take place?
I have questions about how Project Connect construction will affect my business or residence?
Why is the City spending money to grind down what seems like perfectly good pavement on Hollister Avenue in Old Town when other roads need repaving and are in worse shape?
Old Town Goleta has always had street parking, but many cars park overnight. With the Hollister Old Town Interim Striping Project adding 90-minute parking, will the City start enforcing parking limits
How many net new parking spaces will the Hollister Old Town Interim Striping Project add?
What are the goals of the Hollister Old Town Interim Striping Project?
Why does the Hollister Old Town Interim Striping Project include back-in angled parking instead of conventional pull-in parking?
What happens if the Hollister Old Town Interim Striping Project causes an increase in traffic?

Environmental Requirements

As with all construction projects, the City was required to assess the project’s environmental impacts in advance of construction. Mitigation efforts were incorporated into the engineering design and approved by regulators, and the construction team abides by environmental requirements for air quality, nesting birds, land clearing, water way work, among others.

Project Connect construction requires the removal of certain trees and plants within the project area. However, the City of Goleta is committed to creating and enhancing its sensitive habitats and the environmental landscape in a manner that exceeds the total acreage and plant species impacted by Project Connect. The implementation of the City’s comprehensive mitigation efforts will result in a more diverse, abundant and expanded native ecological footprint within the City of Goleta.

By the Numbers

When complete, plant and biological restoration efforts will result in:

  • More than 5 acres (5.34 acres) of enhanced or newly created riparian habitat and areas where additional trees will be planted, which is a net gain in the acreage of coastal and non-coastal riparian habitat within the City of Goleta.
  • 10 trees planted for every tree removed, for a total of 1,980 new California native trees
  • Restoration or creation of riparian habitat at a ratio of 3:1 for permanent riparian impacts and 2:1 for temporary riparian impacts caused by the project

The mitigation plantings will be completed at the end of the construction project in 2026.

Environmental Impact Report
Native Plant Selection and Non-Native Plant Removal
Maintenance and Plant Protection
Restoration Area Locations

Project Timeline

Questions:
Call: 805-690-5116
Email: Connect@CityofGoleta.org